AI Summary
Tyler与Greg在回应分析师提问时明确表示,Black Pearl、Barbara Lake及Stingray三个站点的许可已基本到手,项目可按既定时间表交付并开始收租。要点如下:
- 已向Black Pearl交付18兆瓦IT负载,向Barbara Lake交付51兆瓦,两处均为已签约租赁。
- Stingray为已签约租赁,正在安装并推进开发;仅有雨水等非实质性许可待批,无需听证程序。
- Barbara Lake的土方与外壳施工将于Q4启动,管理层称无任何理由认为项目会延期交付或无法稳定运营。
- Black Pearl的256英亩扩地被视为增加选择权,未来可能同时服务表前与表后场景,公司将持续在 pipeline 站点周边囤地。
- Barbara Lake因成本通胀与人工上涨,每兆瓦IT资本开支从1040万美元升至1230万美元,收益率一度从15.2%降至12.9%。
- 公司通过将租约延长10年(追加投资后资本开支达每兆瓦1300万美元),把收益率拉回15.2%,管理层称这是被市场误读的重要战略交易。
- 分析师推测该租户为Anthropic(与Cipher、Fluid Stack有联合公告),并追问非投资级前沿实验室是否需要类似Google/Fluid Stack的信用背书;管理层以侦探比喻回应,未直接确认租户身份。
- 管理层强调公司为上市公司,前瞻性陈述受安全港规则保护,并建议参考官网投资者页面的财报电话会。
结论:三个站点交付节奏与许可风险可控,Barbara Lake租约延期是保住收益率的关键安排;投资者应关注非投资级租户的信用增信安排而非短期市场情绪。
Transcript
And there's Barbara Lake and there's Stingray.
Those are contracted leases that are starting to be installed and further along in development.
So I guess my question for both of you guys following the election in the state of
Texas with the new governor elect with Black Pearl.
You've delivered 18 megawatts of IT, delivered 51 megawatts at Barbara Lake and you've started
earthworks or earthworks grading and shell construction are beginning in Q4.
High level question for all those sites.
Are all the permits in hand and do you see any reason why those projects can't be completed
and stabilized and begin to be delivered on time so that they can, so the respective tenants
can pay rent?
Yeah, I don't see any issues to delivering those on this schedule we mentioned on the earnings
call.
So you're right.
We've got and I guess sorry let me just do a little hygiene before I get started at the
requests of folks keep in mind.
We are a public company.
Please refer to our earnings call.
You can find a link to it on our website under the investors tab and I won't read an entire
disclaimer but of course if we make any forward looking statements on this discussion I know
it's being recorded.
We would certainly avail ourselves of the rules around safe harbors and forward looking
statements under the securities laws.
So that's good housekeeping.
Sorry.
I'm sorry you're answering your question.
No, I think everything should be set as we laid out in the earnings call.
You had the numbers correct for the early delivery at Black Pearl and then the first 51
megawatts we mentioned at Barbara Lake permits are in hand or I believe there may be a few
of them.
So I'll call immaterial permits at stingray that we do not anticipate any issues with the
things around stormwater or something like that.
But nothing that requires like a hearing or something like that.
So we don't have any reason right now to believe that there will be any issues.
Great.
And as a follow up I have one for each site as it pertains to Black Pearl.
I noticed the 256 acre expansion is that something you anticipate being front of the meter or
behind the meter Tyler.
Yeah, I mean, I think that there is the potential over time maybe even for both but certainly
behind the meter I think is attractive at all of our sites.
So having more land just gives us more options in general.
That's a theme.
I think we continue to acquire plots of land at our sites, the ones further out in the
pipeline and the ones that we think eventually we can expand on.
So that's a keen observation.
Appreciate that.
With respect to Barbara Lake.
Notice this is probably a good segue to talk through the what was a larger topic on the
earnings call regarding the lease amendment and additionally the change orders that led
to some additional investment by your team into the property.
So just to get contacts to everyone before asked Tyler, our Greg a question, my understanding
and guys feel free to correct me upon completion.
But essentially the company and budgeted $10.4 million of catbacks for the per IT megawatt
and that grew to 12.3 for a variety of reasons including cost inflation and labor.
Now instead of having their yield on cost drop from 15.2% down to 12.9%, the company opted
to extend the lease to a third party for an additional 10 years, which after that investment
of additional funds raised the catbacks to 13 million per megawatt.
But as a result of that lease amendment, the yield on cost elevated back to 15.2%.
So my question to you guys as it pertains to that is the lease was amended with a frontier
lab which I know you're not at liberty to say who it is, but I'll tell everyone I believe
it's anthropic after cipher, fluid stack and anthropic had a joint announcement to donate
$10 million to believe it's collar for me forget the name of the city, but Colorado city
I believe it is and that's related to the Barbara Lakes site.
So you guys don't have to confirm that it's anthropic, but any event that it is anthropic
or another frontier lab without investment grade credit, is that going to require a new
sort of backstop in the future similar to what you have with Google, and fluid stack.
Let me start and then I'll pass it over to Greg to talk a little bit about this deal because
I think this is a really important strategic deal for the company and I think the market
didn't interpret it in the way we had hoped.
I think we've cleared it up a little bit on our earnings call.
The overall tape has been gross for the sector and I think people have generally been
looking for boogeymen anywhere.
I think I've been pretty disappointed with how this has been received.
So I'm glad we have this opportunity to talk about it and then I will make sure we specifically
answer your specific question.
But you are in a student detective looking at breadcrumbs and I'll just leave the first
statement at that.
What I'd say is when you think about this deal, we had a situation really at all three
of our first sites where we had there was a rush from tenants last fall to get sites secured
quickly.
And so they got to know us, they were doing their diligence, us and other competitor
companies.
And we had sites with either already that were already energized or were soon to be
energized and that got them very excited.
And I think there was a bit of a fomo and so we signed both some groundbreaking deals
to change the company and also just some amazing deals in terms of counterparty and the yields
we were able to get to terms we were able to get.
One of the things that was unique about that situation is they wanted to go so fast and
of course we wanted to transform the entire company so quickly that we were willing to
move forward on what I would call very early stage design sets.
I mean, this was often like a flattened graded site with a substation but like the tenant
was signing up pretty quickly without a fully mature design.
And what that means is we were happy to move forward on those terms but that does present
a situation where you're much more likely to get change orders from the tenant as things
evolve especially in this market where frankly designs are evolving very quickly for these
data centers just in general across the market.
So flash forward to Barbara late so in the case of Barbara Lake, we signed the deal.
In the case of the other two deals we signed with AWS those designs were like so early and
one of them was a retrofit of a Bitcoin mining site that we put in a cost cap in those
two contracts basically saying like this design is so immature any kind of budget framework
we put together is just really early so it's very hard to have that budget mean much if
we don't know how the site design is going to evolve.
But so that that feature was not in the Barbara Lake site and we moved forward and as it
developed we did have a fair number of tenant change orders and so as a result with those
change orders produced that produced an increased cost forecast and the tenant wanted it and
we had the rights to receive reimbursement for it and then also in addition to that change
order set of change orders which was about call it half of the costs that exceeded our
original estimate.
There was another 50% or so that was related to yeah inflation labor supply chain you
know change of scope things like that where if we sat down and penciled out every dollar
you know maybe some of it falls on the tenant some of falls on cipher but it's not as
cut and dried as like a change order okay and so that's the nature of the evolution of
the budget at the site.
Now flash forward we have the right to go seek reimbursement for those change orders to
say hey you know you switch things around and made the budget go up as much send us this
much money.
In this case as you know the lease is with fluid stack it has that Google backstop that
you mentioned and there is an end AI lab involved there in terms of taking the compute
from the site and so working with those counter parties we got to a spot where there was a
request to say what if we could come up with a different way to deal with what would
otherwise be change orders and the other cost increases just from you know changes go
things like that is there a framework where cipher would be willing to invest more equity
in the site right now in exchange for something is there a proposal that you could make because
we would love to not send this cash out right now just given where we are in our own you
know corporate evolution is there something where we could make it win win and look credit
really to Greg here I think we came up with a great structure which was we will do that we
will front and inject capital to finish the project including dollars that you would otherwise
be responsible for but we want to tweak the deal and the way we tweaked it is we basically matched
the what would be the forecasted cost overage to bring the economics either back in line or
improve versus the original deal so basically on on every financial metric we improved the deal by
extending it to a 20 year lease and then ultimately changing in that second 10 years facing the AI lab
and and so a couple things to note and then I promise I'm coming back to answer your question
so from our perspective we preserved the outstanding economics in the deal or improved them I mean
we get a vast amount of rent now being paid to us over 20 years um you know you asked about sort
of the credit rating of the AI lab all I'd say is we'll have to see where that goes but the AI
lab is certainly a much much larger entity with much more cash on balance sheet uh then fluid stack and
that's not anything negative about fluid stack that's just a factual statement so when we think about
like credit risk 10 to 20 years out there are some attractive features to that um so that's something
that's very attractive we increased all the financial metrics on the deal and I think most importantly
from my seat look we think that AI lab is going to be arguably the most important co-location tenant
in the world going forward um probably for the rest of my professional career so coming up with a
way that was like a win-win at their request um I believe really sets the table for us to continue
to deepen that relationship and it's my hope we have ambitions to do a lot more with them so
I think from a qualitative perspective it's a huge strategic win for us from a quantitative
perspective it's great and with that I'll pass it to Greg Greg if you want to talk a little bit
more about the financial metrics or talks specifically about um the credit backstop and how that works
with the debt at the site yeah for sure I mean first of all that was a fantastic overview always
always hard to follow um so everybody I'm coming to you live actually right now from a couple
conferences I'm actually at the Cantor conference today in the JP Morgan conference tomorrow I think
I'm meeting 110 12 investors over the two day period so spending a lot of time talking about these
these items and certainly you know a lot of the questions that I'm sure this community is going to
ask and you guys you guys do your work and you do great work so something that I'm excited about as
you know the finance nerd on the call or one of them at least is something that's really overlooked
with respect to this transaction so yes Tyler mentioned the return profiles improved you know
huge amount of rent that's been added we've changed the counter party and added a second half
but I think what's really interesting here is as you know the flywheel requires you to recycle capital
out of the projects that you've completed so if you're not recycling capital and you know reinvesting
that capital in a non-delutive way into the pipeline projects you're not really getting the full
impact of the flywheel and the business proposition doesn't create as much value as it could otherwise
so why this is really important is because on the initial 10 year lease where we had the declining
Google Backstop it was really a challenging proposition to think that we could go and take
additional leverage after completing the site because the Google Backstop was structured to decline
in line with our initial construction debt so to go and take additional debt above that construction
financing and try to recycle capital you would be taking fluid stack exposure on top of the Google
Backstop so now you go from a situation where you weren't really able to based on the structure of
the initial deal and initial backstop you weren't able to recycle capital you're now talking about a 20
year lease where the second half is now facing one of the largest AI labs in the world you know we
can have a debate over where that ends up from a credit perspective in 10 years but it doesn't matter
for the first 10 years because we still have the Google Backstop but let's say in a couple years that
you know that lab